15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

What is the term for words such as after, before, following, and then in the chronological writing process? A. signal words B. indefinite pronouns C. conjunct
Each leg of a 45-45-90 triangle has a length of 6 units. What is the length of its hypotenuse?
You are working at establishing a computer network and communications support for incident personnel. Where are you working? a. Operations Section b. Planning S
A criticism of the American system of federalism is that it is
how many times is 5 bigger than 0.5?
The instantaneous velocity of an object is the blank of the object with a blank
Susan deposits $1,200 in an account that earns 8% simple interest annually. In how many months will Susan's account balance reach $1,344? (Use the simple intere
Milwaukee is 121 mi (air miles) due west of Grand Rapids. Maria drives 255 mi in 4.75 h from Grand Rapids to Milwaukee around Lake Michigan. Find her average dr
round 44,769 to the nearest ten
round 9,254 to the nearest hundred