raazshah661 raazshah661
  • 03-09-2020
  • Mathematics
contestada

A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

Jen recently rode her bicycle to visit her friend who lives 6 miles away. On her way there, her average speed was 8 miles per hour faster than on her way home.
When a proposed merger between two companies is reviewed by the government, the relevant market is defined by ________.
Determine the measure of the interior angle at vertex C. PLEASE HELP ASAP
Automobile airbags inflate due to the formation of nitrogen gas from the chemical reaction 2NaN3(s)—> 3N2(g)+2Na(s) Identify the number of each atom in the r
chapter 3 reactivity of metals mcq question and question and answer and important notes? ​
I have to go to…….bank today to deposit some money. (put the correct article in the blank space)​
write 7 087 000 in standard form​
if you are the principal of your school how do you manage all staffs​
What is the following product? Assume d>0 3vd•3vd•3vd
She ....a shower in bathroom.(Fill in the blanks with simple present/present continuous form of the verb have